In the 1970s, power companies began building many new coal-fired electrical power plants in the Ohio Valley to feed the growing industry in that region. These power plants were close to coal mines, so the electricity they generated was less expensive than nuclear or hydroelectric. One such new power plant was to be built on Willow Island, West Virginia.

Around 10:00 a.m. on 27 April 1978, workers engaged in the building of the second 430-foot concrete cooling plant began hoisting their third load of wet concrete from the ground to the work platform, 166 feet in the air. Without warning, the top of the partially constructed tower collapsed into the center of the tower, killing 51 construction workers. A worker on the ground near the tower, who helped in the rescue effort, told newspapers, “I looked and it was gone. The scaffolding was just gone.”

To date, the partial collapse of the Willow Island Cooling Tower is considered the worst construction accident in the United States. Why did it occur?

 

What Caused this Disaster?

Use of concrete with insufficient compressive strength. The builders used concrete to support the scaffolding system of the cooling tower, but began subjecting it to the load of tower construction, including the dynamic loads of hoisting operations, only 18 hours after it had been poured. Subsequent reports estimated the insufficiently cured concrete had a compressive strength of 220 pounds per square inch (psi), where the required mechanical strength to support the construction of higher tower sections was calculated (after the accident) to be more than 1,000 psi. In any case, the builders should have planned to provide a safety factor of two in their design – meaning they should have let the supporting concrete of the lower portion of the tower cure until its compressive strength was over 2,000 psi.

Missing bolts/bolts too weak for the load. The traditional method of construction was to base the scaffolding on the ground and build it up to keep up with the height of a structure, but the building plan of the Willow Island cooling towers was to bolt the scaffolding required for each higher section of tower to the concrete tower structure below. An investigation by OSHA after the disaster found that there were bolts missing from the scaffolding (which also supported the crane that collapsed) and that the bolts used had insufficient strength to secure the scaffolding to the concrete.

Moving the anchor point for the static line. The hoisting system for lifting concrete to construct higher portions of the tower uses a static line running from the load to the ground. The static line keeps the load from swinging and, by requiring an extra pulley for routing the line, assists in lifting by reducing the mechanical force needed to raise the load. The static line runs through an anchor point on the ground, from which it is pulled to lift the load. Initially, the anchor point was close to the base of the tower (i.e., the static line was nearly vertical), but was moved for construction convenience away from the wall to the center of the cooling tower, creating a side-force on the gantry that helped collapse the tower. The subsequent accident report notes,

If the base anchor point of the static line had been kept at its previous location (before the last move to near the center of the tower), the effects of the construction loads would have been reduced to such an extent that the failure of lift 28 of the tower would probably not have occurred.

No person or group was responsible for safety at the site. The construction plan was to support the construction equipment, which included concrete forms for higher sections of the tower, lifts for raising concrete, and the workmen, on the already-built lower sections of the wall. However, the builders never specified either how long the concrete sections had to cure or how much tested strength was required before work could begin on the higher sections of the tower. Although a testing company on-site performed mechanical tests on the concrete, “nothing in their contract would seem to indicate they would have any authority to shut the job down if they found problems,” as reported by a Governor’s Commission. The commission further reported, “there were no inspectors or supervisors of any kind on the job whose responsibility it was to check the work to make the determination either to proceed with the work or give the concrete more time to gain strength.”

Lack of training for construction workers. The builders provided no training in what, for many construction workers, was a new kind of construction system. Using already-constructed sections of the tower to support higher scaffolding was common on steel-framed buildings but relatively uncommon on concrete buildings. The Governor’s Commission commented, that because of the word-of-mouth training that is a natural part of the work environment and because there were no written specifications available for reference, workers could inadvertently make gradual modifications that might compromise the design and cause conditions beyond the limitations of the materials.

Some of the inadvertent modifications that helped cause the collapse included the moving of the anchor point of the static line, as the tensions of various loads helped maintain the strength of the scaffolding.

 

Effects of the disaster

During the hoisting of the third load of concrete to the construction site 166 feet above the ground, the static line suddenly and ominously went slack. The gantry then fell off the top of the tower into the center, and the concrete tower section poured the previous day started collapsing; the whole tower section began “unwrapping” off the tower. The metal scaffolding, the wooden cranes, and the most recently poured tower section all fell as a jumble into the center of the tower. All 51 construction workers on the tower itself died during the collapse.

Immediately after the disaster, the remaining workers on the site rushed to dig for their colleagues. Fire departments from five surrounding municipalities were called in to assist in rescue efforts, and one nearby fire department’s garage was turned into a temporary morgue. Many of the workers who died could only be identified by the contents of their pockets, and one of the workers was never found.

There were multiple investigations after the disaster. The Governor’s Commission focused on the safety culture, noting the lack of worker training as well as the lack of management and technical supervision. An investigation by the Occupational Health and Safety Administration (OSHA) identified mistakes in construction technique, particularly emphasizing that the concrete was not allowed to cure and the bolts securing the scaffolding were too weak (and some were missing).

On 8 June 1978, OSHA issued the construction company a “knowing and intentional” violation of safety practices citation “for failure to make field tests on field-cured concrete specimens to ensure that the concrete had attained sufficient strength to safely support the load prior to removal of the forms.” The citation was settled for $83,000.